Uploaded image for project: 'ZABBIX BUGS AND ISSUES'
  1. ZABBIX BUGS AND ISSUES
  2. ZBX-18669

If you get your Problem solved DURING maintenance preirod which happened BEFORE maintenance period, Recovery operations action will be executed even [Pause operations for suppressed problems] is checked in action configuration

    XMLWordPrintable

Details

    • Documentation task
    • Status: Closed
    • Trivial
    • Resolution: Fixed
    • 4.0.26
    • 5.4 (plan)
    • Server (S)
    • None
    • Team D
    • Sprint 70 (Nov 2020), Sprint 71 (Dec 2020)

    Description

      If you get your Problem solved DURING maintenance preirod which happened BEFORE maintenance period, Recovery operations action will be executed even [Pause operations for suppressed problems] is checked in action configuration.
      Is this expected ? If it is expected behavior, I think its conflict with below description.

      During a maintenance “with data collection” triggers are processed as usual and events are created when required. However, problem escalations are paused for hosts/triggers in maintenance, if the Pause operations for suppressed problems option is checked in action configuration. In this case, escalation steps that may include sending notifications or remote commands will be ignored for as long as the maintenance period lasts.

      https://www.zabbix.com/documentation/4.0/manual/maintenance

      Attachments

        Activity

          People

            martins-v Martins Valkovskis
            yIn Syusei YIn
            Votes:
            0 Vote for this issue
            Watchers:
            3 Start watching this issue

            Dates

              Created:
              Updated:
              Resolved: