-
Documentation task
-
Resolution: Fixed
-
Trivial
-
4.0.26
-
None
-
Sprint 70 (Nov 2020), Sprint 71 (Dec 2020)
If you get your Problem solved DURING maintenance preirod which happened BEFORE maintenance period, Recovery operations action will be executed even [Pause operations for suppressed problems] is checked in action configuration.
Is this expected ? If it is expected behavior, I think its conflict with below description.
During a maintenance “with data collection” triggers are processed as usual and events are created when required. However, problem escalations are paused for hosts/triggers in maintenance, if the Pause operations for suppressed problems option is checked in action configuration. In this case, escalation steps that may include sending notifications or remote commands will be ignored for as long as the maintenance period lasts.