      Imagine weekly maintenance with period 02:00-12:00 on Sunday. It is expected that EACH Sunday, a group of hosts undergoes automatic maintenance tasks for 10 hours.
      But in case of DST change, 02:00 can be skipped and there is no maintenance at all.

      Please, consider if this behavior is worth changing.