Uploaded image for project: 'ZABBIX BUGS AND ISSUES'
  1. ZABBIX BUGS AND ISSUES
  2. ZBX-24304

Initiate Maintenance even if start time skipped by DST.

XMLWordPrintable

    • Icon: Incident report Incident report
    • Resolution: Unresolved
    • Icon: Major Major
    • None
    • None
    • Server (S)
    • None

      Imagine weekly maintenance with period 02:00-12:00 on Sunday. It is expected that EACH Sunday, a group of hosts undergoes automatic maintenance tasks for 10 hours.
      But in case of DST change, 02:00 can be skipped and there is no maintenance at all.

      Please, consider if this behavior is worth changing.

            zabbix.dev Zabbix Development Team
            atocko Andrey Tocko
            Votes:
            1 Vote for this issue
            Watchers:
            3 Start watching this issue

              Created:
              Updated: