The step duration of operations has problem if using default value

    XMLWordPrintable

    Details

      Description

      The step duration of operations has problem if configuring escalation in action. (Configuration=>Actions=>Create action=>Operations=>New)

      Below explanation is based on the documentation: https://www.zabbix.com/documentation/3.0/manual/config/notifications/action/operation:
      Step duration - custom duration for these steps (0=use default step duration). Several operations can be assigned to the same step. If these operations have different step duration defined, the shortest one is taken into account and applied to the step.

      But in my test, it didn’t use the shortest one if setting one of the step duration to default(0).

      Please check the attachment.

      Br
      Matt Ye

        Attachments

        1. xxx.png
          xxx.png
          46 kB
        2. zabbix.png
          zabbix.png
          115 kB

          Activity

            People

            Assignee:
            Unassigned
            Reporter:
            yezgmg Matt Ye
            Votes:
            0 Vote for this issue
            Watchers:
            4 Start watching this issue

              Dates

              Created:
              Updated:
              Resolved: